Washington will have a completely rebuilt stadium but keep its iconic site on the shore of Lake Washington.
Photos by:UNIVERSITY OF WASHINGTON

Washington

Husky Stadium
Built: 1920
Project cost: $250 million
Renovation designer: 360 Architecture
Last major renovation: 1987

The two-year construction project is halfway done in Seattle, with structural steel completion set for Oct. 3. The Pac-12 school is essentially getting a new stadium at the spot where its old one sat, at one of college football’s most beautiful settings on the shores of Lake Washington. The project is adding 25 suites, 45 patio suites and 2,500 outdoor club seats on the stadium’s south side.

Where it stands: School officials took a conservative approach for suite development, said O.D. Vincent, Washington’s senior associate athletic director; total premium inventory represents only 6 percent of total seats. “We knew we weren’t going to sell 100 suites ringing the bowl,” he said. “I think we have the right number of premium seats.” When the project is completed, stadium seating will be reduced to about 70,500. The loss of 2,000 seats were mostly obstructed views, Vincent said. The running track circling the field will be removed, bringing fans much closer to the action in what is already one of college football’s loudest stadiums. Washington plays home games this season at CenturyLink Field before moving back to Husky Stadium next season.

Premium seat details: Suites (18 seats) $60,000 annually for three or five years; 17 of 25 sold in early September. Patio suites (logestyled product) $10,000 annually for four seats, $15,000 annually for six seats, both for three or five years; sold out. Club seats $1,050-$1,950 annual donation plus cost of season tickets; sold out. Parking passes included, food and drink a separate cost for all premium seats.

Financing: The university is marketing 12 founding partnerships to help pay for construction. Two deals offer naming rights to the field and the new club. Project funding is split among $50 million in private donations and $200 million financed through the sale of 30-year bonds.

SBJ Morning Buzzcast: June 6, 2024

New leaders at LA28 and WTA Tour and one year later on PGA Tour and LIV Golf

Fox Sports’ Joel Klatt, Stanley Cup Final puck drop, and a hectic week for ESPN

On this week’s pod, Joel Klatt joins the show to talk all things UFL and college football. The Fox Sports football analyst shares his thoughts on the future of spring football and the changing landscape on the college gridiron. Later in the show, SBJ’s Alex Silverman gets us set for the Stanley Cup Final between the Edmonton Oilers and Florida Panthers. Plus, Mollie Cahillane fills us in on who’s up and who’s down in sports media.

One on One with Chatri Sityodtong, Founder and CEO of Group ONE

A chat getting to know Chatri Sityodtong...his background, the rise of ONE Championship and his vision.

Shareable URL copied to clipboard!

https://www.sportsbusinessjournal.com/Journal/Issues/2012/09/24/Facilities/Washington.aspx

Sorry, something went wrong with the copy but here is the link for you.

https://www.sportsbusinessjournal.com/Journal/Issues/2012/09/24/Facilities/Washington.aspx

CLOSE