BALTIMORE SUN PUTS FINAL BILL FOR CAMDEN COMPLEX OVER $500M

          The final figures are not complete, but "it appears the
     Ravens' stadium will end up costing" $223M, putting the cost
     of Baltimore's two-stadium complex at more than $500M,
     according to Jon Morgan of the Baltimore SUN.  The football
     price tag is "slightly above projections from even last
     year," but it does include some items paid for by the team
     and other organizations.  It does not include the "nearly"
     $6M light rail station or the costs of the land underneath
     the building.  With those costs included, including half the
     Camden Yards land, the football project will cost about
     $279M, with interest on the bonds used to finance the
     project to total about $100M over the next 30 years.  MD
     Stadium Authority Exec Dir Bruce Hoffman said construction
     costs will "probably stay at" $223M.  Morgan reports that
     when the deal was signed to bring the Browns to Baltimore in
     '95, the state agreed to spend $200M on a stadium.  Now, if
     the football estimate holds up, the total Camden Yards
     project will end cost a total of $502.5M, "more than twice
     the estimates" made when lawmakers passed the funding
     measure in '86, "although the football stadium was built
     years later than anticipated after inflation had driven up
     all costs."  Construction of Oriole Park cost $106.5M, with
     the team contributing $9M to the ballpark (SUN, 8/12).
          GREEN THUMB: The Ravens have installed the SportGrass
     Athletic Surfacing in their new stadium, which was grown at
     the Greg Norman Turf Farms in Avon Park, FL (SportGrass).
     

SBJ Morning Buzzcast: May 3, 2024

Seismic change coming for NCAA? Churchill Downs rolls out major premium build out and Jeff Pash, a key advisor to Roger Goodell, steps down

Learfield's Cory Moss, MASN/ESPN's Ben McDonald, and Canelo

On this week’s pod, SBJ’s Austin Karp has two Big Get interviews. The first is with Learfield's Cory Moss as he talks about his company’s collaboration on EA Sports College Football. Later in the show, we hear from MASN/ESPN baseball analyst Ben McDonald on how he sees the college and professional baseball scene shaking out. SBJ’s Adam Stern shares his thoughts on the upcoming Canelo-Mungia bout on Prime Video and DAZN.

SBJ I Factor: Molly Mazzolini

SBJ I Factor features an interview with Molly Mazzolini. Elevate's Senior Operating Advisor – Design + Strategic Alliances chats with SBJ’s Ross Nethery about the power of taking chances. Mazzolini is a member of the SBJ Game Changers Class of 2016. She shares stories of her career including co-founding sports design consultancy Infinite Scale career journey and how a chance encounter while working at a stationery store launched her career in the sports industry. SBJ I Factor is a monthly podcast offering interviews with sports executives who have been recipients of one of the magazine’s awards.

Shareable URL copied to clipboard!

https://www.sportsbusinessjournal.com/Daily/Issues/1998/08/12/Facilities-Venues/BALTIMORE-SUN-PUTS-FINAL-BILL-FOR-CAMDEN-COMPLEX-OVER-$500M.aspx

Sorry, something went wrong with the copy but here is the link for you.

https://www.sportsbusinessjournal.com/Daily/Issues/1998/08/12/Facilities-Venues/BALTIMORE-SUN-PUTS-FINAL-BILL-FOR-CAMDEN-COMPLEX-OVER-$500M.aspx

CLOSE