NBA ADMITS TO KEEPING A CLOSE EYE ON RAPTORS STADIUM DELAY

     Extensions of agreements between the Raptors and the City of
Toronto and Marathon Realty over a new C$200M arena project are
due to expire on September 30 which will result in a C$1M fine
for the team for the second consecutive year, according to Craig
Daniels of the TORONTO SUN.  Without agreements in place, the
team can not close its property purchase from Canada Post, owner
of the stadium site.  One source close to the talks noted that
"if they can't close, they can't build."  NBA Deputy Commissioner
Russ Granik told the CANADIAN PRESS, "Certainly, if September 30
comes and goes, we will be watching."  Team President John Bitove
confirmed the September 30 fine date, but called NBA concerns "no
big deal."  According to a source close to the project, financing
is not the reason for the delays: "The money is there.  The
problem has been getting the team's board to agree to financing
terms."  Construction on an arena would have to begin by early
November in order to be ready for the '98-99 season and another
extension on the September 30 (TORONTO SUN, 9/20).
     ARENA IN JEOPARDY?  The NBA's Granik said penalties --
financial and others -- could be "imposed should the startup of
the project" continued to be delayed.  The fine "should be the
least" of the team's worries, according to Doug Smith of the
CANADIAN PRESS.  Besides the fine, "bigger concerns are
agreements that won't exist in perpetuity." Raptors President
Bitove "could not say how many of the more than 200 legal
documents would unravel if another construction deadline is
missed."  On reported speculation concerning a deal to share a
facility with the Maple Leafs, Bitove said, "We have not had any
serious discussions with the Leafs."  Bitove also ruled out
tenancy with the Leafs:  "We're building ... so there's no point
in discussing tenancy with anyone" (CP/Toronto GLOBE & MAIL,
9/20).

SBJ Morning Buzzcast: April 24, 2024

Bears set to tell their story; WNBA teams seeing box-office surge; Orlando gets green light on $500M mixed-use plan

TNT’s Stan Van Gundy, ESPN’s Tim Reed, NBA Playoffs and NFL Draft

On this week’s pod, SBJ’s Austin Karp has two Big Get interviews. The first is with TNT’s Stan Van Gundy as he breaks down the NBA Playoffs from the booth. Later in the show, we hear from ESPN’s VP of Programming and Acquisitions Tim Reed as the NFL Draft gets set to kick off on Thursday night in Motown. SBJ’s Tom Friend also joins the show to share his insights into NBA viewership trends.

SBJ I Factor: Molly Mazzolini

SBJ I Factor features an interview with Molly Mazzolini. Elevate's Senior Operating Advisor – Design + Strategic Alliances chats with SBJ’s Ross Nethery about the power of taking chances. Mazzolini is a member of the SBJ Game Changers Class of 2016. She shares stories of her career including co-founding sports design consultancy Infinite Scale career journey and how a chance encounter while working at a stationery store launched her career in the sports industry. SBJ I Factor is a monthly podcast offering interviews with sports executives who have been recipients of one of the magazine’s awards.

Shareable URL copied to clipboard!

https://www.sportsbusinessjournal.com/Daily/Issues/1996/09/20/Facilities-Venues/NBA-ADMITS-TO-KEEPING-A-CLOSE-EYE-ON-RAPTORS-STADIUM-DELAY.aspx

Sorry, something went wrong with the copy but here is the link for you.

https://www.sportsbusinessjournal.com/Daily/Issues/1996/09/20/Facilities-Venues/NBA-ADMITS-TO-KEEPING-A-CLOSE-EYE-ON-RAPTORS-STADIUM-DELAY.aspx

CLOSE